Every couple of weeks, we share what we’re seeing across the Puget Sound custom-home market — the trends, costs, and shifts that actually affect a build in Snohomish County and across the greater Puget Sound. This issue is about a date six months out that decides which rules a house in design today will be built under, and what has to be finished before it.
On May 3, 2027, new building codes take effect, and the permit application decides which ones apply
Washington’s 2024 building codes, including a new residential energy code, take effect May 3, 2027. The State Building Code Council is still finishing the text: the building and residential codes have not had their final vote, and the energy codes are set for November 20. The Council has set May 3, 2027 as the date all of them take effect.
Which codes your house is reviewed under is not decided by when design starts. Under state law, a “valid and fully complete” building permit application is considered under the building codes in effect on the date it is submitted. A house still on the drafting table on May 3 is a house built to the new codes.
“Complete” is a high bar on a rural lot
In unincorporated Snohomish County, a complete application is more than a set of house plans. The county’s residential permit bulletin lays out what goes with it. On a lot served by septic, the Health Department has to approve the water supply and waste disposal plans for new construction. Structural plans and a site plan are reviewed alongside zoning and critical areas, and drainage goes through its own separate permit. The energy code calculations go in with the first set of plans for any residential permit. The application is not deemed complete and accepted until the intake fees are paid.
The septic piece alone has its own clock. The Health Department currently lists five weeks to review a new septic application and four weeks for construction clearance, and it does not accept expedited applications. That review cannot start until a licensed designer has evaluated the site and drawn the system.
Counting back from May 3
Two schedules run before a custom home reaches a complete application, and it helps to see them separately.
The first is architectural design. When an architect is drawing custom plans, that stage alone commonly runs six months to a year. It can go faster when the owners start with a strong, clear concept, and slower as the house grows in size and detail or as decisions change along the way.
The second is the pre-planning work that takes finished plans to a complete permit submittal. In our experience that takes four to seven months on its own.
Run back to back, the two add up to roughly ten to nineteen months. They do not have to run back to back. When we sign a Feasibility and Construction Agreement with the client at the start of architectural design, much of our pre-planning runs alongside the design instead of after it, overlapping about a third of the design stage. That brings the total closer to eight to fifteen months, and it keeps the design, the site work and the budget moving together instead of meeting for the first time at the end.
Now count back from May 3, 2027. With finished or stock plans already in hand, starting the pre-planning between early October and early January can still reach a complete application in time. With a custom design starting from scratch, the window to start was roughly February through early September of this year. A custom design that begins now will almost certainly be permitted under the new codes, and is better off designed to them from the first sketch.
Issuance is a separate clock and does not change which codes apply. Snohomish County typically takes about three more months to issue the permit, and an issued permit is valid for 18 months, renewable once for another 18. Getting in under the current codes buys time to build, not an open-ended exemption.
The energy code is where the complexity has grown most
Of everything in a permit set, the energy code has become the most involved part. Beyond the baseline insulation, window and air-sealing requirements, every new house has to earn a set number of energy credits chosen from a list of measures. The 2024 version raises the bar again: it tightens air leakage to 3.0 air changes per hour, lowers the window U-factor to 0.27, adds credit requirements in steps by house size, and requires ducts inside the conditioned part of the house or deeply buried in insulation. That last one changes a floor plan rather than a specification.
That is why the energy work is best done inside the design, not after it. When the architect runs the energy calculations as the plans develop, the measures that earn credits are designed in. Done afterward, they turn into revisions: resizing windows, dropping one, moving a door. The same goes for stock plans. A plan drawn under an older code may need changes before it can meet the current one, let alone the next.
What it costs depends on the house. The Building Industry Association of Washington’s own analysis estimates the new code slightly lowers first cost for an average 2,376-square-foot home heated with a heat pump, but adds about $25,300 for a comparable home heated with gas. If your plans call for gas heat, that difference belongs in the budget from the start.
None of this means the new codes are something to escape. Whether a house is designed to the current codes or the new ones should be a decision made at the start, not something discovered at submittal.
Snohomish County has 44% more homes for sale than a year ago
Snohomish County’s median closed price in September was $720,000, with active listings up 44.2% from a year earlier, the second-largest increase of any county in the Northwest MLS. In King County, the median was $850,000, unchanged from a year ago. For anyone weighing an existing house against a build, there is more to choose from than there has been in some time.
What This Means for Prospective Clients
If you are thinking about building in the next year, the calendar matters more than usual. The date that decides your code is the day the county accepts a complete application, and on a rural lot that takes months of design, septic and site work to reach. With plans in hand, this fall is still early enough to choose. With a custom design just beginning, the choice is effectively made, and the better move is to design to the new codes on purpose.
We’re a small firm by design. We work with a limited number of clients each year, and we take the time to get the project right. If you’re curious about what custom design-build actually looks like — the process, the timeline, the decisions — we’re happy to talk.
Ready to Build Your Custom Home?
Talk to us about your vision. We build custom homes throughout Snohomish County.
Contact Us